Member Content
Figure
Published
Share

Allen & Overy: e-Alert – Is the future of wind farms at risk?

Overview

This e-Alert discusses the current debate on environmental impact assessments for wind farms. This debate was triggered by recent case law of the European Court of Justice. Opponents of wind farms have argued that this case law has put the future of wind farms in the Netherlands at risk. For the reasons discussed in this e-Alert we believe that this risk is very limited.

Introduction

On 22 October 2020, the District Court of Noord-Nederland rendered its much-anticipated judgment in injunction proceedings initiated by wind farm opponents.[1] These proceedings were triggered by a European Court of Justice (ECJ) judgment dated 25 June 2020 in Case-24/19, ECLI:EU:C:2020:503, on the requirement to prepare an environmental impact assessment (milieueffectrapportage (MER); an EIA). In the Dutch media, wind farm opponent first argued that this ECJ judgment could significantly impact wind farms. Now they have also brought this argument to court.

Relevant legal framework and the 25 June 2020 ECJ judgment

An EIA contains a detailed assessment of a project’s impact on the environment and ensures that the environmental impact is considered in the decision making process. The requirement to prepare an EIA follows from EU Directives and has been further detailed in national legislation. Under the relevant EU Directives, an EIA is required for “plans or programmes” that are likely to significantly effect on the environment, that are prepared and adopted by national, regional or local authorities, and that are required under public law provisions. They must also set out a framework for future projects listed in the Annexes to the relevant EU Directives, such as wind farms.

The 25 June 2020 ECJ judgment originates from a dispute before Belgium courts and relates to an Order and a Circular for the development of onshore wind farm projects adopted by the Flemish government. The Order contained general environmental conditions on nuisance and other risks related to wind turbines. The Circular listed several elements that had to be taken into account when deciding whether to allow for the installation of wind turbines, such as grouping, land use, habitat, agriculture, industrial land, noise impact, shadow cast, safety and nature. The ECJ was asked whether the Order and Circular qualified as “plans or programmes” and should therefore have been subject to an EIA.

The ECJ ruled that the Order and Circular should have been subject to an EIA. In reaching this conclusion, the ECJ considered that a broad interpretation of “plans and programmes” is required in order to serve the purpose of the EU Directives of protecting and improving the environment. Decisions regulated by public law provisions that determine which authorities are competent to adopt them and the procedure for preparing them may qualify as plans or programmes. The general or abstract nature of a decision or measure does not prevent a decision or measure from being a “plan or programme”.

Current debate

Following the aforementioned ECJ judgment, wind farm opponents argue – via the Dutch media — that this judgment may have significant consequences for existing and future wind farms. In particular, they argue that the ECJ judgment confirms that the requirement to prepare an EIA may also follow from general environmental rules on noise and shadow cast laid down in the Dutch Activities Decree (Activiteitenbesluit milieubeheer), which apply by operation of law to wind farms in the Netherlands. Based on this argument, opponents initiated injunction proceedings before the District Court of Noord-Nederland, asking the District Court to put the development and operation of wind farm “De Drentse Monden and Oostermoer”, located in the Province of Drenthe and consisting of 45 wind turbines, on hold for violating the EIA requirements under EU laws.

The District Courts’ judgment of 22 October 2020

The District Court did not address the merits of the case. Instead, the District Court declared the injunction proceedings inadmissible for not complying with the formal requirements under Dutch civil law for initiating legal proceedings by interests groups. The District Court did add an obiter dictum, however, by referring to an important principle of Dutch law with respect to irrevocable permits obtained for a particular project. This principle entails that an irrevocable permit must be deemed to be lawful with respect to both its content and procedure. According to the District Court, the only remaining route for opponents is submitting a request to the competent authorities to withdraw an integrated environmental (operating) permit (omgevingsvergunning). They could base such request on the argument that EU laws were violated.

Further analysis

For the following reasons, we doubt whether the competent authorities would be obliged to grant a request to withdraw an irrevocable permit. It is true that the ECJ has frequently emphasized in its case law that Member States, including the national courts, are required to take all general and particular measures necessary to rectify a violation with EU law within the sphere of their competence. As the ECJ also noted in its 25 June 2020 judgment, this means that a plan or programme will have to be suspended or annulled. However, we have also identified several counter-arguments leading to the conclusion that Dutch wind farm permits are not at great risk:

  • Most decisions required for wind farm development in the Netherlands are already subject to an EIA. Dutch implementing legislation designates activities and (planning) decisions for which an EIA (MER-plicht), an EIA assessment (MER-beoordelingsplicht) or a so-called form-free EIA (vormvrije MER-beoordeling) is required, depending on the size and capacity of a wind farm:
    • An EIA is required for wind farms consisting of at least 20 wind turbines;
    • An EIA-assessment is required for wind farms larger than 15 MW or with at least 10 turbines; and
    • A form-free EIA is required for wind farms up to 15 MW but with at least 3 wind turbines.
    • Accordingly, for most wind farms in the Netherlands, an EIA or related assessment has already been prescribed and carried out.
  • It is also questionable whether the general environmental rules under the Activities Decree trigger the requirement to prepare an EIA. Dutch courts have already rejected a similar argument in previous proceedings. According to the Dutch Council of State (Afdeling bestuursrechtspraak van de Raad van State), a “plan or programme” must be linked to particular projects. The general environmental rules on noise and shadow cast do not meet this requirement, as these rules are of a general nature, meaning that they apply to all wind turbines in the Netherlands once they are operational, and cannot be considered as conditions for granting consent for wind farms in specific geographical zones or particular wind farm projects.[2]
  • Although the ECJ has acknowledged that Member States, including the national courts, are required to take all the necessary measures to remedy EU law violations, the case law of the ECJ also emphasizes the principle of legal certainty. The principle of legal certainty is particularly relevant for completed wind farms put into operation based on irrevocable permits and for which, as noted, an EIA was prepared. According to the ECJ, the principle of legal certainty should be given considerable weight. Any new case law on the scope and interpretation of EU law does, in principle, not affect the legality of irrevocable permits.[3]
  • The ECJ has also allowed for an exemption from the obligation to take all necessary measures to remedy an EU law violation. According to the ECJ, if a plan or program’s annulment would lead to a legal vacuum that is incompatible with other obligations under EU laws concerning the protection of the environment, national courts are allowed to maintain the legal effects of such a plan or program.[4]
  • In addition, the ECJ accepted that a failure to carry out an EIA may be remedied by preparing an additional assessment. According to the ECJ, an additional assessment can be an adequate instrument to “regularise” omissions in a prior assessment or a lack of such assessment. Such assessment should not only address the project’s future environmental impact, but must also account for its environmental impact since the time that project was completed.

Conclusion

As the District Court of Noord-Nederland’s recent 22 October 2020 judgment has not addressed the merits, it is unlikely that this judgment will end the current debate on the alleged EIA requirement under the Dutch Activities Decree for wind farms. However, for the reasons discussed above, we do not expect that recent ECJ case law risks the future of existing and future wind farms in the Netherlands.

Read the original article here. Find out more about Allen & Overy here.

Share this Article
Featured
Holland Fintech Digital Transformation Paper 2024
Holland Fintech is proud to present the Digital Transformation Paper 2024. This whitepaper, led by the Holland Fintech working group Digital Transformation in collaboration with Accenture, provides valuable insights into the dynamics and key factors influencing successful collaborations between fintechs and incumbents.
Holland Fintech Pavilion at Money 20/20
Money 20/20 – Join our Pavilion! The Holland Fintech Pavilion offers a unique opportunity to connect with a global audience of fintech professionals. Located at the heart of Money 20/20, the pavilion provides a central hub for networking, collaboration, and exposure.
Amsterdam Fintech Week
Amsterdam FinTech Week is back on 2-4 October 2024! Be a sponsor, co-organizer, or just participate in our community events.

How likely are you to recommend Holland FinTech?